Selected Projects
Projects where independent oversight made a difference.
Each engagement below involved a specific technical risk that required independent verification. Client names are withheld by agreement.
15 MW Biomass CHP — Commissioning Verification
Independent commissioning supervision and performance testing prior to formal owner acceptance.
Thermal output deficit of 11% identified versus contract specification. Contractor required to remediate before handover was signed.
District Heating Network — Technical Supervision
On-site technical supervision during reconstruction of a 12 km district heating network including pump stations and substations.
14 non-conformances documented and resolved during construction phase. Zero punch list items carried into warranty period.
Industrial Boiler House — Energy Audit
Measurement-based energy audit of a 6 MW industrial boiler house including combustion analysis and distribution losses.
Identified 18% efficiency improvement potential. Prioritised action plan delivered with 2.1-year average payback.